Quebec Line Rebuild Project

Quebec Line Rebuild Project

Working hard to improve reliability for customers in Western North Carolina.

Project Background

The Quebec Line Rebuild Project plans to upgrade power lines to help improve reliability and resiliency, accommodate future growth, and better enable the integration of cleaner energy options and innovative technologies. We want to share our plans with customers and answer any questions about this project.

Community Benefits

These grid investments will help our customers in many ways now and for many years to come.
  • Meet Growing Energy Demand in the Region

  • Reduce Outages and Strengthen Reliability

  • Minimize Impacts By Using Existing Easements Where Possible

  • Help Promote Cleaner Sources of Energy

Project Timeline*

The Quebec Line Rebuild Project is a 6.6-mile project to update and construct transmission structures. Work will start in the spring of 2025 and is scheduled to be completed in the summer of 2029.

*Dates are tentative and schedule is subject to change.

Preconstruction Phase

Surveying/Permitting
Present  5/1/2025
 
Vegetation Management
Spring 2025 – Fall 2025
 
Soil Boring
Spring 2025 – Fall 2025 

Construction Phase

Construction
Late Spring 2026 – Fall 2028
 
Restoration
Spring 2027 – Summer 2029

Project Map

Quebec Line Reliability Improvement Project Map Showing Construction Phases

Watch Our Videos to Learn More

Learn more about the importance of transmission and how it plays a vital role in powering our communities.
icon question

Frequently Asked Questions

Image

Contact Us

Please call 800.365.8979 or email CarolinasWest@duke-energy.com.

Additional Resources

Here is more background and detailed information about the Quebec Line Reliability Improvement project. These may help answer your questions