Skip to Content

Wildwood Heights Substation and Underground Line

Wildwood Heights Substation and Underground Line

Current Project Activities

Duke Energy is in the early planning stages for a new substation in St. Petersburg, Fla., and an approximately 1/4-mile underground transmission line that will connect the substation to an existing transmission line to the west. In the coming months, project neighbors may notice crews surveying, staking, conducting soil testing and digging to identify underground utilities and performing other field investigations.

Project Overview

St. Petersburg is experiencing rapid growth and an increasing need for energy. To help provide safe and reliable electricity to those who live and work in St. Petersburg, we are building a new substation in south St. Petersburg that will bring a new source of power to the area and directly serve the residents of the community.

Project Details

  • The substation will be located on a 1.75-acre parcel at 1295 28th St. in St. Petersburg. 
  • An approximately 1/4-mile underground transmission line will connect the new substation along 13th Avenue South to the existing transmission to the west. 
  • The new substation is a gas-insulated technology, a modern design where the equipment is safely enclosed inside a building compared to typical outdoor substations.
  • This type of substation is more compact and requires less land to build, offering aesthetic benefits by being housed in a structure that can be designed to blend into the community.
Image

Benefits to the Community

  • Enhanced reliability for St. Petersburg neighborhoods and businesses

  • Increased energy supply to directly serve south St. Petersburg

  • Helps reduce outages and impacts of storms

  • Supports growth and future prosperity of community

Project Map

Placeholder graphic at 960 pixels wide by 540 vertical
View and download a pdf version of the map.

GIS Photo Simulation

Placeholder graphic at 960 pixels wide by 540 vertical
The image above is a conceptual design for the new substation. The final design including landscaping and fencing will be completed closer to construction and with community feedback.

Timeline

  • Preconstruction work, including surveying, staking, soil boring and vegetation removal begins

    March 2025

  • Construction begins

    2026

  • Project completion and restoration

    2027

Timeline is subject to change based on factors such as weather, availability of crews and equipment or unforeseen circumstances that may impact the schedule.

Watch Our Videos to Learn More

What to Expect During Construction

The first phase of construction will involve removing any vegetation, structures or other obstructions on the substation site and in the road to allow safe access for crews and equipment during construction.

Neighbors can expect construction equipment such as cranes, excavation equipment, trucks and concrete mixers in the project area. Security lighting and fencing may be used during construction.

The installation of underground facilities and substations is challenging and complex. The 1/4-mile power line will be located underground in road right of way. 

During the construction of the line, there will be excavation of the corridor/road to allow for the installation of the new underground line. Maintenance vaults and manholes will be installed along the underground transmission line route. Following construction, the roadway will be repaved and properties will be restored as closely as possible to their original conditions. The line will not be visible above ground, and equipment will be maintained through the underground vaults. 

Appropriate safety protocols will be followed, and work zones will be clearly marked. It will be important for the public to avoid work zones and drive slowly in areas where crews are working.

 
icon question

Frequently Asked Questions

icon conversation

Questions?

icon documents

Additional Resources