Project Overview & Need

New Infrastructure Facts

  • Work will be done in phases:
    • Phases 1 and 2 are complete.
    • Phases 3-5 will be completed in 2025 through 2028.
  • See Interactive Map
  • Constructed of a more robust steel with a fusion-bonded epoxy coating to prevent corrosion
  • Built-in state-of-the-art safety inspection features

Project Overview and Need

  • Replace and Upgrade Existing Natural Gas Infrastructure
    The 70-plus year-old natural gas infrastructure will be replaced with a modern pipeline constructed from stronger materials with state-of-the-art monitoring equipment and inspection technology. Replacing infrastructure that has been around since the 1950s is the prudent thing to do.
  • Regulatory Compliance
    Our system must be upgraded from time-to-time to maintain compliance with federal regulations. 
  • Enhance Our Natural Gas System
    The upgraded pipeline will enhance our natural gas system, helping to continue providing safe and reliable service to Northern Kentucky customers for decades to come.

Project Filing and Oversight

A Certificate of Public Convenience and Necessity (CPCN) was filed for each phase. Applications for future phases will be filed once design on each phase is finalized.

  • Phase 1 was filed with the Kentucky Public Service Commission (KYPSC) in April 2022 and was granted in March 2023.
  • Phase 2 was filed with the KYPSC in June 2023 and was granted in April 2024.
  • Phase 3 was filed with the KYPSC in June 2023 and was granted in January 2025.
  • Phase 4 was filed with the KYPSC March 13, 2025. We expect to have the permit granted in Fall 2025.