Skip to Content

Powerline – Holder Transmission Line Project

Project Overview

Duke Energy plans to construct a new transmission line to help meet the anticipated growth in Citrus County.

Project Details

  • Construct a new 11.5-mile, 230-kilovolt (kV) transmission line between the new Powerline Substation in Crystal River, Fla., and the existing Holder Substation in Beverly Hills, Fla.
  • The transmission line will be built on single-circuit monopole structures, typically ranging from 90 to 95 feet above ground, with a few structures reaching 140 feet above ground.
  • All but 0.5 miles will be built within existing right of way. All Holder substation work will be performed inside the existing substation fence line.

Benefits to the Community

  • Enhance the ability of Duke Energy and neighboring utilities to provide safe and reliable energy to homes, community facilities and businesses in the area.
  • Provide flexibility and additional capacity to continue delivering reliable electricity to meet the region's growing energy needs.
  • Maintain a robust system for supplying and delivering energy which is integral to the continued economic prosperity of the region.

What to Expect

Once a project is announced, there are several key steps that take place during the design and pre-construction phases of a transmission line project. During early stages of field investigation, residents may see Duke Energy staff and contractor field crews in the area evaluating existing conditions. This field data is crucial in assisting our engineering teams and other personnel with the design and construction planning for the project. After the field investigation is complete, our engineering team will develop the design for the project.

If a new easement or an update to the current easement is required, a company representative will contact the property owner to discuss the easement process. Additionally, we will be assessing the need to clear obstructions and vegetation within the current easement to prepare for construction. Property owners will be notified in advance should either of these issues need to be addressed.

Construction activities are anticipated to begin in fall 2021 and be completed in May 2023.

 

Key Dates

  • Public Notifications

    November 2018

  • Real Estate Activities Started

    February 2019

  • Construction Begins

    Fall 2021

  • Restoration of Right of Way

    To be completed after construction

  • In-service Date

    May 2023

icon transmission wires

Transmission and what we do

 Watch our short video to learn more about the importance of transmission and how it plays a vital role in powering our communities.

Image

Have a Question or Comment?

Email us at MPPReliability@duke-energy.com
Call at 877.552.8725
Or write Duke Energy Public Engagement
NP4B
3300 Exchange Place
Lake Mary, FL 32746

Additional Resources